Project Overview
Client: Peter Ballantyne Cree Nation
Location: Deschambault Lake, Sk
Value: $5,000,000.00
Start Date: October 2024
Completion Date: August 20, 2025
Schedule: 10 months
CandorBuild Role: Prime Contractor
Delivery Method: Lump Sum
Prime Consultant: RBM Architecture
About the Project
This project involved the construction of a new 5,200 sq. ft. cultural classroom in a remote location. Unique challenges included complex logistics and lodging coordination for crews and materials. Despite these constraints, construction was completed efficiently and finished 18 days ahead of schedule. The project showcased a strong commitment to planning, adaptability, and timely delivery in an isolated environment.